South East upgrade

After investing £1.25bn to improve the railway in Kent and South East London between 2019 and 2024 our work to modernise the network for passengers continues with a planned £1.35 billion investment over the next five years.

The funding will tackle historic under-investment in the Kent network, replacing ageing equipment with new and more reliable technology to support improving train performance and keeping people moving for decades to come.

Key statistics

£310 million on track and junctions

£309 million on signalling work

£133 million on earthworks

£44 million on drainage improvements

£167 million on electrical and power supply improvements

£213 million replacing or refurbishing our structures

£128 million on buildings

Upgrade work

Keeping you on the move

Record investment means that we’ll be doing more work to improve the railway than ever before.  We’ll do most of the work when trains are not running,  but will need to work at weekends and on bank holidays.

If you are planning to travel at the weekend or on a bank holiday, please don’t get caught out.  Always check before you travel at National Rail enquiries or with your train operator, Southeastern or Thameslink.

Key projects

Hither Green Aerial View
We’re installing a new footbridge with four new lifts and staircases. The creation of two new entrances will provide step-free access between platforms. As part of the Department for Transport’s (DfT) nationwide Railway Access for...
Shortlands-CGI-1
We have installed three new lifts and a new footbridge at Shortlands station, to provide step-free access between platforms.  As part of the Department for Transport’s nationwide Railway Access for All strategy, we installed a...
Inside-the-Blackheath-Tunnel
From Sunday 18 May to Sunday 27 July 2025, the Blackheath tunnel between Blackheath and Charlton was closed as Network Rail undertook £10m of essential repairs to the 175-year-old Victorian-era structure. The work this year,...
HungerfordBridge1
We'll be carrying out essential work to refurbish the Hungerford railway bridge. Many of the bridges, tunnels and viaducts on Britain’s railway are from the Victorian era. Being responsible for this national heritage is both...
Lewisham-track-and-junctions
We're replacing the signalling on the south east London lines running through Lewisham, from New Cross to Blackheath and Hither Green.    The old 1970s signalling equipment will be replaced with the modern and more reliable...
Landslip in Surrey work in Dec 2023
Between Friday 18 and Monday 21 April 2025, engineers began landslip prevention works at Chislet between Canterbury West and Minster. We undertook earthwork repairs on the slope that forms the cutting for the railway. We...
Peckham Rye station redevelopment
Passengers using Peckham Rye station can look forward to a brighter, easier to use station thanks to a £5 million investment from Department for Transport, Southwark Council and the Railway Heritage Trust that will transform...

Sign-up for email updates

Sign-up with your email address to receive updates on the South East upgrade and information on projects taking place across the Southern region.

Our privacy notice applies to the personal information that Network Rail collects about you, or that you provide to us. It explains how and why we use your personal information, who we disclose it to and how we protect your privacy.

Contact us

For more information or to get in touch with us, please contact us by visiting our contact us page or by calling our 24-hour national helpline on 03457 11 41 41.