Bradwell site
Bradwell sits on a 20 hectare site on the Essex coastline, and has played a pioneering role in the UK’s nuclear decommissioning mission. Selected in 2009 for accelerated decommissioning, the site made history less than a decade later when it became the first UK nuclear facility to enter ‘care and maintenance’ (C&M) – a landmark moment for the industry.
This achievement followed an extensive programme of ground breaking decommissioning work, including the removal of all historically stored nuclear wastes and redundant plant, the demolition of aging buildings and assets, and the safe removal of conventional hazards such as asbestos. New purpose‑built facilities were constructed to ensure the site remains safe, secure and resilient throughout the C&M period.
Bradwell is remotely managed by the Sizewell A team, who carry out regular maintenance inspections and maintain a 24‑hour security presence.
In pictures












Key facts
1957
Construction began
1965
Generation started
2002
Generation ended
2008
Defueling started
2011
Turbine Hall demolished
2012
Defueling ended
2015
Administration complex demolished
60
Total output TWhrs
2
Number of reactors
0 hectares
Land released of re-use