Skip to content

Bradwell site

Bradwell sits on a 20 hectare site on the Essex coastline, and has played a pioneering role in the UK’s nuclear decommissioning mission.  Selected in 2009 for accelerated decommissioning, the site made history less than a decade later when it became the first UK nuclear facility to enter ‘care and maintenance’ (C&M) – a landmark moment for the industry.

This achievement followed an extensive programme of ground breaking decommissioning work, including the removal of all historically stored nuclear wastes and redundant plant, the demolition of aging buildings and assets, and the safe removal of conventional hazards such as asbestos. New purpose‑built facilities were constructed to ensure the site remains safe, secure and resilient throughout the C&M period.

Bradwell is remotely managed by the Sizewell A team, who carry out regular  maintenance inspections and maintain a 24‑hour security presence.

In pictures

Key facts

1957

Construction began

1965

Generation started

2002

Generation ended

2008

Defueling started

2011

Turbine Hall demolished

2012

Defueling ended

2015

Administration complex demolished

60

Total output TWhrs

2

Number of reactors

0 hectares

Land released of re-use